Safety Operating Regulations for DTH Rock Drilling Posts
1. Carefully check and handle blast holes and pumice before operation, and do a good job of sprinkling and dust removal, and work under safe conditions.
2. Level the work site and remove obstacles.
3. When installing the machine, it must conform to the center position and angle of the measuring point, and construct according to the design.
4. Check the sleepers used for the uprights, the quality of the stows, flatten the pads firmly, and tighten the fixing screws to prevent deflection and collapse and injury.
5. All screws should be checked frequently and tightened at any time to prevent injury from tripping.
6. The operating table and the machine are forward and reverse (forward rotation tunneling, reverse shackle).
8. When opening eyes, people must stand in a safe area to operate.
9. When replacing the drill bit and the drill pipe, the machine must be stopped, and the two inserts must be inserted firmly to prevent flying out and hurting people and the drill pipe falling off and hurting people. Clamp it with a clamp, pay attention to the occlusion, and do not extend the foot under the machine rod. , One must avoid the direction of the hole.
10. The thrust of the propeller should not be too large to prevent the drill rod from breaking, when handling the clamp rod, to prevent sudden drop and injury, and to prevent the platform from falling when moving the equipment.